_______
Prescott Passive House
At the start of this week, students were able to receive the framing package for the Prescott Passive House and began cutting the necessary members. A quick break in winter weather also allowed us to put down gravel and the first three layers of under-slab insulation. More snowstorms have put us back in the warehouse planning, preparing and pre-fabricating so that we will be ready to move into action on-site with the remaining concrete work and framing as soon as weather permits.