Over the week, the first interior walls were constructed.  These walls are especially important in our design, because they are where our plumbing and venting will run for all of our bathrooms.  Most of the interior walls will be framed with 2x4 studs, however in order to accommodate for plumbing, these first walls are framed in 2x6.  The construction of all of our interior walls will be in wood reclaimed from the Sunflower Ammunition Plant.

 